Dome installed on Tianwan 6 containment building
2018-5-10

The containment dome of unit 6 of the Tianwan nuclear power plant in China's Jiangsu province was installed on 5 May, marking the reactor's entry into the equipment installation phase of construction, China Nuclear Engineering and Construction Corporation (CNECC) announced today. CNECC is a subsidiary of China National Nuclear Corporation (CNNC).

Tianwan 6 dome installation - 460 (CNEC)
Installation of the containment dome at Tianwan 6 (Image: CNECC)

Installation of the 148-tonne dome was completed at 3:49pm on 5 May and completes the civil construction phase of the project. The operation to lift the dome 60 meters above ground level and to lower it into place on top of the walls of the containment building took 53 minutes to complete, CNECC said.

Construction of Tianwan Phase III - units 5 and 6 - was originally scheduled to start in early 2011. However, following the March 2011 accident at Japan's Fukushima Daiichi plant, the Chinese government suspended the approval of new nuclear power projects, including those two units.

The latest Five-Year Plan called for construction of Phase III of the Tianwan plant to be accelerated. China's State Council gave its approval for Tianwan units 5 and 6 - both featuring 1080 MWe ACPR1000 reactors - on 16 December 2015. First safety-related concrete was poured for unit 5 on 27 December 2015, with that for unit 6 poured on 7 September 2016.

CNNC plans to put both units 5 and 6 into commercial operation by the end of 2021.

Tianwan Phase I - units 1 and 2 - was constructed under a 1992 cooperation agreement between China and Russia. First concrete was poured in October 1999, and the units were commissioned in June 2007 and September 2007 respectively. Tianwan Phase II - units 3 and 4 - are similar to the first stage of the Tianwan plant, comprising two Russian-designed 1060 MWe VVER-1000 pressurised water reactors. First concrete for unit 3 was poured in December 2012, while construction of the fourth unit began in September 2013. Unit 3 achieved first criticality on 29 September last year and was connected to the grid on 30 December. The unit completed demonstration operation at nominal capacity for 100 hours on 15 February and is scheduled to enter commercial operation later this year. Unit 4 is expected to begin operating in March 2019.

The Tianwan plant is owned and operated by Jiangsu Nuclear Power Corporation, a joint venture between CNNC (50%), China Power Investment Corporation (30%) and Jiangsu Guoxin Group (20%).

  
 
2018-5-18
Belgium and China award simulator contracts
2018-5-18
Progress for WIPP infrastructure upgrade
2018-5-18
Perry scraps completion of US MOX facility
2018-5-18
Rosatom expands overseas links with new agreements
2018-5-18
NWMO broadens its international cooperation
2018-5-11
FirstEnergy responds to PJM grid reliability findings
2018-5-11
Nuclear for US grid resilience and climate
2018-5-10
Dome installed on Tianwan 6 containment building
2018-5-10
Other signatories express support for JCPOA
2018-5-10
TVA completes major flood protection
2018-5-8
Robots get smarter to help with decommissioning
2018-5-4
Fuel supply contracts signed for Swedish reactors
2018-5-4
New cracks delay restart of Hunterston B reactor
2018-5-4
Training milestones for new plant operators
2018-5-4
First Energy responds to PJM grid reliability findings
2018-5-4
NASA successfully tests Kilopower reactor
2018-4-27
Philippines to draw up nuclear energy policy
2018-4-27
IAEA reviews safety at South Ukraine unit 3
2018-4-27
Fuel loading under way at Chinese AP1000
2018-4-27
Macron: Europe must prioritise emission reductions
2018-4-27
Iran's Bushehr I changes to TVS-2M fuel
2018-4-20
6th Annual Nuclear Information Technology China Forum
2018-4-20
2nd Nuclear Power Maintenance Tool Seminar
2014-9-19
The Preparation Meeting of the First International Nuclear Plant Operation and Maintenance Conference 2014 Successfully held in Shanghai.
2014-9-19
NNBCS2014 Concluded a Great Success on August 27-29 in Shanghai!
2014-7-21
China's Xi hails 'new horizons' in ties with Argentina
2014-7-21
China nuclear contractor seeks merger with CPIC
2014-7-11
Investment program for Slovenian repository
2014-7-11
Supercomputer team wins award for core work
2014-6-17
Chinese Premier expected to sign UK nuclear deal
2014-6-17
Changjiang 2 vessel put in place
2014-6-13
Fourth Yangjiang unit gets its dome
2014-6-13
Sogin, CGN cooperate on waste management
2014-6-13
China produces first AP1000 vessel
2014-6-12
The 6th Annual Nuclear New Build China Summit
2014-6-6
Fuel loading at Fuqing 1
2014-6-6
China schedules new nuclear power reactors
2014-6-6
Fukushima ice wall under construction
2014-6-3
China Association of Plant Engineering Consultants
2014-5-27
China, Iran agree to push bilateral cooperation to new stage
2014-5-12
Mining operations begin at Husab
2014-5-9
Yangjiang 2 approaches start up
2014-5-8
Ningde 2 in commercial operation
2014-5-4
MBIR reactor supplier selected
2014-4-28
Political discord places Lungmen on hold
2014-4-28
Landmarks for Chinese reactors
2014-4-22
The 6th Annual Nuclear New Build China Summit 2014 will start up on August 27th in Shanghai, China!
2014-4-22
NITF2014 Concluded a Great Success on April 10-11 in Shanghai!
2014-4-22
Accelerating the Progress of Nuclear Power Informatization, building a safe and high-efficiency operation environment! —NITF 2014 will Start up on April 10-11, 2014 in Shanghai, China!
2014-4-22
Expanding Your Company’s Value in Nuclear IT Industry——The 2nd Annual Nuclear Information Technology China Forum 2014 is Coming Back!
About Us
Who We Are
Our Culture
Nuclear Summit
Event Center
Professional Service
Industry Information
Project Consulting
Training Course
Event Outsourcing
Join Us
Job Opportunities
Career Development
Contact Us
Tel: (+86-21) 6073 7200
Fax: (+86-21) 6176 8133
Email: info@innchinc.com
 
© 2018 INNCH INTERNATIONAL CO.,LTD. All Rights Reserved 技术支持:上海网站建设