US governor releases report on VC Summer flaws
2017-9-7

US governor releases report on VC Summer flaws

Bechtel Corp highlighted "significant issues" at the VC Summer project 18 months before construction of two AP1000 reactors at the site in Fairfield County, South Carolina, was scrapped in July. Difficulties, such as flawed construction plans, faulty designs, inadequate management and low worker morale, were outlined in the engineering, construction and project management company's independent analysis of the project dated February 2016.

On 31 July, Scana Corporation subsidiary South Carolina Electric & Gas (SCG&E) announced its decision to cease construction of the two Westinghouse-designed units at VC Summer. The announcement followed co-owner Santee Cooper's decision to suspend construction because of projected completion delays and cost overruns.

Bechtel's report was released by South Carolina Governor Henry McMaster's office on 4 September against objections from Santee Cooper's lawyers, who asked the governor not to place it in the public domain.

Issues

According to Bechtel's project assessment report for VC Summer, there were eight significant issues facing the project:

• While the consortium's engineering, procurement and construction plans and schedules are integrated, the plans and schedules are not reflective of actual project circumstances;

• The consortium lacks the project management integration needed for a successful project outcome;

• There is a lack of a planned vision, goals and accountability between the owners and the consortium;

• The contract does not appear to be serving the owners or the consortium particularly well;

• The detailed engineering design is not yet completed, which will subsequently affect the performance of procurement and construction;

• The issued design is often not constructible, resulting in a significant number of changes and causing delays;

• The oversight approach taken by the owners does not allow for real-time, appropriate cost and schedule mitigation;

• The relationship between the consortium partners (Westinghouse Electric Company (WEC)) and Chicago Bridge & Iron (CB&I)) is strained, caused to a large extent by commercial issues.

Recommendations

Bechtel's recommendations included creating a new "more achievable" project schedule.

The owners should develop an Owner's Project Management Organisation and supplement current owner staff with additional EPC-experienced personnel, it said. The owners and consortium should "align contract commercial conditions with the project goals and determine the realistic to-go forecast costs for project completion". The consortium should complete a "new, more achievable" project schedule. It should remove the "mandatory constraints" from the Integrated Project Schedule and allow the schedule to move "based on the logic". It should prioritise the development of mitigation/recovery plans based on their impact to the schedule, it said. It should also ensure appropriate time is allocated for the installation of bulk commodities (large and small bore piping, pipe supports, cable tray, conduit, cabling).

The consortium should "initiate a focused effort to complete WEC known engineering 'debt' and release the over 1000 drawing holds that exist"; intensify the efforts of the Strategic Planning group, work package planning, constructability reviews etc. to identify design changes needed well in advance of the construction need date; and stay on top of identifying and resolving emergent technical issues.

The consortium should also increase manual staffing levels to allow working of all available work areas, and evaluate methods "to have the craftsmen spend more time at the workface". It should implement actions "to improve craft productivity and retention, and simplify and streamline work packages", the report said.

In addition, Bechtel recommended that the consortium "complete the inventory revalidation effort and establish a program to continually validate the inventory". And it should "complete the procurement schedule adherence effort to ensure equipment delivery dates meet construction need dates".

Michael Bexley, senior vice president and general counsel at Santee Cooper, wrote to McMaster on 3 September, providing the Bechtel report as requested and asking that its contents remain confidential. McMaster's office said in a statement on 4 September the governor "believes there is no basis for their 'assertion of privilege' or confidentiality".

Westinghouse filed for Chapter 11 protection from creditors in late March to enable strategic restructuring amid "financial and construction challenges" in its US AP1000 power plant projects.

VC Summer is one of two projects to build Westinghouse AP1000 pressurised water reactors in the USA. The other is Georgia Power's Vogtle plant under construction near Waynesboro in Georgia.

On 31 August, Georgia Power filed a recommendation with the Georgia Public Service Commission to complete construction of Vogtle units 3 and 4 as the most economic choice for customers. The company expects unit 3 to begin commercial operation in November 2021 and unit 4 in November 2022.

Construction of all four US AP1000s - VC Summer and Vogtle - began in 2013.

Researched and written
by World Nuclear News

  
 
2018-5-18
Belgium and China award simulator contracts
2018-5-18
Progress for WIPP infrastructure upgrade
2018-5-18
Perry scraps completion of US MOX facility
2018-5-18
Rosatom expands overseas links with new agreements
2018-5-18
NWMO broadens its international cooperation
2018-5-11
FirstEnergy responds to PJM grid reliability findings
2018-5-11
Nuclear for US grid resilience and climate
2018-5-10
Dome installed on Tianwan 6 containment building
2018-5-10
Other signatories express support for JCPOA
2018-5-10
TVA completes major flood protection
2018-5-8
Robots get smarter to help with decommissioning
2018-5-4
Fuel supply contracts signed for Swedish reactors
2018-5-4
New cracks delay restart of Hunterston B reactor
2018-5-4
Training milestones for new plant operators
2018-5-4
First Energy responds to PJM grid reliability findings
2018-5-4
NASA successfully tests Kilopower reactor
2018-4-27
Philippines to draw up nuclear energy policy
2018-4-27
IAEA reviews safety at South Ukraine unit 3
2018-4-27
Fuel loading under way at Chinese AP1000
2018-4-27
Macron: Europe must prioritise emission reductions
2018-4-27
Iran's Bushehr I changes to TVS-2M fuel
2018-4-20
6th Annual Nuclear Information Technology China Forum
2018-4-20
2nd Nuclear Power Maintenance Tool Seminar
2014-9-19
The Preparation Meeting of the First International Nuclear Plant Operation and Maintenance Conference 2014 Successfully held in Shanghai.
2014-9-19
NNBCS2014 Concluded a Great Success on August 27-29 in Shanghai!
2014-7-21
China's Xi hails 'new horizons' in ties with Argentina
2014-7-21
China nuclear contractor seeks merger with CPIC
2014-7-11
Investment program for Slovenian repository
2014-7-11
Supercomputer team wins award for core work
2014-6-17
Chinese Premier expected to sign UK nuclear deal
2014-6-17
Changjiang 2 vessel put in place
2014-6-13
Fourth Yangjiang unit gets its dome
2014-6-13
Sogin, CGN cooperate on waste management
2014-6-13
China produces first AP1000 vessel
2014-6-12
The 6th Annual Nuclear New Build China Summit
2014-6-6
Fuel loading at Fuqing 1
2014-6-6
China schedules new nuclear power reactors
2014-6-6
Fukushima ice wall under construction
2014-6-3
China Association of Plant Engineering Consultants
2014-5-27
China, Iran agree to push bilateral cooperation to new stage
2014-5-12
Mining operations begin at Husab
2014-5-9
Yangjiang 2 approaches start up
2014-5-8
Ningde 2 in commercial operation
2014-5-4
MBIR reactor supplier selected
2014-4-28
Political discord places Lungmen on hold
2014-4-28
Landmarks for Chinese reactors
2014-4-22
The 6th Annual Nuclear New Build China Summit 2014 will start up on August 27th in Shanghai, China!
2014-4-22
NITF2014 Concluded a Great Success on April 10-11 in Shanghai!
2014-4-22
Accelerating the Progress of Nuclear Power Informatization, building a safe and high-efficiency operation environment! —NITF 2014 will Start up on April 10-11, 2014 in Shanghai, China!
2014-4-22
Expanding Your Company’s Value in Nuclear IT Industry——The 2nd Annual Nuclear Information Technology China Forum 2014 is Coming Back!
About Us
Who We Are
Our Culture
Nuclear Summit
Event Center
Professional Service
Industry Information
Project Consulting
Training Course
Event Outsourcing
Join Us
Job Opportunities
Career Development
Contact Us
Tel: (+86-21) 6073 7200
Fax: (+86-21) 6176 8133
Email: info@innchinc.com
 
© 2018 INNCH INTERNATIONAL CO.,LTD. All Rights Reserved 技术支持:上海网站建设