Sanmen 2 completes hydrostatic testing
2017-9-6

   Sanmen 2 completes hydrostatic testing

The second AP1000 unit under construction at the Sanmen site in China's Zhejiang province has completed cold hydrostatic testing of its primary circuit. The tests are an important step in the commissioning of new units.

Sanmen units 1 and 2 (Image: SNPTC)

Cold hydrostatic testing involves filling the reactor's primary circuit with water, which is circulated at high pressure by the reactor coolant pumps to verify that the welds, joints, pipes and components of the reactor coolant system and associated high-pressure systems meet regulatory standards. The coolant pumps will help to maintain the reactor's internal temperature at a safe level during operations.

State Nuclear Power Technology Company (SNPTC) announced yesterday that cold hydrostatic testing began at 0.59am on 2 September. The pressure within the circuit was gradually raised to a maximum of 21.6 MPa and held at that level for 10 minutes. At 10.15am, the pressure was reduced to 17.5 MPa while all the welds and mechanical connections were checked. The tests were completed at 2.00pm the same day.

Similar tests were completed at unit 1 of the Sanmen plant in May 2016, while those at unit 1 of the Haiyang plant in Shandong province were completed in July 2016.

Sanmen 1 is expected to be the first Westinghouse AP1000 to begin operating later this year, while Haiyang 1 is also expected to begin operating by the end of the year. Sanmen 2 and Haiyang 2 are expected to start up in 2018.

Four AP1000 reactors were also being built in the USA - two each at Vogtle and Summer. However, construction of the two Summer units was suspended last month.

Researched and written
by World Nuclear News

  
 
2018-5-18
Belgium and China award simulator contracts
2018-5-18
Progress for WIPP infrastructure upgrade
2018-5-18
Perry scraps completion of US MOX facility
2018-5-18
Rosatom expands overseas links with new agreements
2018-5-18
NWMO broadens its international cooperation
2018-5-11
FirstEnergy responds to PJM grid reliability findings
2018-5-11
Nuclear for US grid resilience and climate
2018-5-10
Dome installed on Tianwan 6 containment building
2018-5-10
Other signatories express support for JCPOA
2018-5-10
TVA completes major flood protection
2018-5-8
Robots get smarter to help with decommissioning
2018-5-4
Fuel supply contracts signed for Swedish reactors
2018-5-4
New cracks delay restart of Hunterston B reactor
2018-5-4
Training milestones for new plant operators
2018-5-4
First Energy responds to PJM grid reliability findings
2018-5-4
NASA successfully tests Kilopower reactor
2018-4-27
Philippines to draw up nuclear energy policy
2018-4-27
IAEA reviews safety at South Ukraine unit 3
2018-4-27
Fuel loading under way at Chinese AP1000
2018-4-27
Macron: Europe must prioritise emission reductions
2018-4-27
Iran's Bushehr I changes to TVS-2M fuel
2018-4-20
6th Annual Nuclear Information Technology China Forum
2018-4-20
2nd Nuclear Power Maintenance Tool Seminar
2014-9-19
The Preparation Meeting of the First International Nuclear Plant Operation and Maintenance Conference 2014 Successfully held in Shanghai.
2014-9-19
NNBCS2014 Concluded a Great Success on August 27-29 in Shanghai!
2014-7-21
China's Xi hails 'new horizons' in ties with Argentina
2014-7-21
China nuclear contractor seeks merger with CPIC
2014-7-11
Investment program for Slovenian repository
2014-7-11
Supercomputer team wins award for core work
2014-6-17
Chinese Premier expected to sign UK nuclear deal
2014-6-17
Changjiang 2 vessel put in place
2014-6-13
Fourth Yangjiang unit gets its dome
2014-6-13
Sogin, CGN cooperate on waste management
2014-6-13
China produces first AP1000 vessel
2014-6-12
The 6th Annual Nuclear New Build China Summit
2014-6-6
Fuel loading at Fuqing 1
2014-6-6
China schedules new nuclear power reactors
2014-6-6
Fukushima ice wall under construction
2014-6-3
China Association of Plant Engineering Consultants
2014-5-27
China, Iran agree to push bilateral cooperation to new stage
2014-5-12
Mining operations begin at Husab
2014-5-9
Yangjiang 2 approaches start up
2014-5-8
Ningde 2 in commercial operation
2014-5-4
MBIR reactor supplier selected
2014-4-28
Political discord places Lungmen on hold
2014-4-28
Landmarks for Chinese reactors
2014-4-22
The 6th Annual Nuclear New Build China Summit 2014 will start up on August 27th in Shanghai, China!
2014-4-22
NITF2014 Concluded a Great Success on April 10-11 in Shanghai!
2014-4-22
Accelerating the Progress of Nuclear Power Informatization, building a safe and high-efficiency operation environment! —NITF 2014 will Start up on April 10-11, 2014 in Shanghai, China!
2014-4-22
Expanding Your Company’s Value in Nuclear IT Industry——The 2nd Annual Nuclear Information Technology China Forum 2014 is Coming Back!
About Us
Who We Are
Our Culture
Nuclear Summit
Event Center
Professional Service
Industry Information
Project Consulting
Training Course
Event Outsourcing
Join Us
Job Opportunities
Career Development
Contact Us
Tel: (+86-21) 6073 7200
Fax: (+86-21) 6176 8133
Email: info@innchinc.com
 
© 2018 INNCH INTERNATIONAL CO.,LTD. All Rights Reserved 技术支持:上海网站建设