2017-9-1

Georgia Power recommends Vogtle completion

Georgia Power has today filed a recommendation with the Georgia Public Service Commission (PSC) to complete construction of Vogtle units 3 and 4 as the most economic choice for customers. The company expects unit 3 to begin commercial operation in November 2021 and unit 4 in November 2022.

Vogtle 3 and 4, pictured in July (image: Georgia Power)

The recommendation, which is supported by the project's co-owners, was made following assessments made after contractor Westinghouse filed for bankruptcy protection in March. These included economic analyses; evaluation of alternatives including abandoning one or both of the AP1000 units or converting them to gas-fired generation; and assumptions related to potential risks including future payments from Toshiba as well as the availability of production tax credits and the extension of federal loan guarantees.

"Based on all factors considered, completing both units represents the most economic choice for customers and preserves the benefits of carbon-free, baseload generation," the company said. The total rate impact of the project remains less than originally estimated, it said.

The Vogtle project is majority owned by Southern Company subsidiary Georgia Power (45.7%), with co-owners Oglethorpe Power (30%), MEAG Power (22.7%) and Dalton city (1.6%). The units will be operated by Southern Nuclear Operating Company.

Georgia Power said it had invested about $4.3 billion in capital costs in the project to June 2017 and estimates its cost to complete to be about $4.5 billion, bringing the company's total capital cost forecast to $8.8 billion. The PSC has already approved $5.68 billion in capital costs for Georgia Power's share of the project. With payments of $1.7 billion under parental guarantees anticipated from Toshiba, Georgia Power's potential additional capital costs are about $1.4 billion. Based on the new assessments, the total estimated capital cost forecast for the entire project is about $19 billion.

Georgia Power's recommendation will be reviewed by the PSC, which may approve, modify or reject the petition. The commission said it expects to do this by mid- to late-February 2018.

Westinghouse CEO José Gutierrez said the company was "very pleased" with Georgia Power's decision. "Georgia Power's continued confidence in AP1000 plant technology strengthens their energy offerings and nuclear's role in America's infrastructure," he said.

Maria Korsnick, president and CEO of the US Nuclear Energy Institute, said Georgia Power's decision signalled a "new era" for nuclear energy in the USA and was a "shot in the arm" for on-site employees and contractors, and the national nuclear supply chain. She called for the US Senate to vote to lift the deadline for the nuclear production tax credit. Under current tax rules the units would need to be brought on line before 1 January 2021 deadline to qualify for credits. "The Vogtle reactors are a national asset that we can ill afford to lose, and the Senate must act quickly to preserve a critical piece of our strategic infrastructure," she said.

Bechtel appointment

Project management and control at the Vogtle site transitioned to Southern Nuclear after a services agreement between Westinghouse and Vogtle's co-owners became effective on 27 July. Georgia Power announced today it has contracted with Bechtel to manage daily construction efforts under the direction of Southern Nuclear.

"We have seen a marked increase in productivity throughout this year, with the best improvement being the most recent improvement, and our experience provides every indication that we can do a better job than Westinghouse alone as we move forward to complete the project," Georgia Power president and CEO Paul Bowers said. "Since Southern Nuclear assumed control of the site from Westinghouse at the end of July, momentum has accelerated with a consistent focus on safe, high-quality construction. We expect this trend to continue with Bechtel."

Construction of Vogtle unit 3 began in March 2013 and unit 4 in November of that year. The units will be the first in the USA to use AP1000 technology following the announcement earlier this month by Scana Corporation subsidiary South Carolina Electric & Gas of its decision to cease construction of two AP1000 reactors at VC Summer.

Researched and written
by World Nuclear News

  
 
2018-5-18
Belgium and China award simulator contracts
2018-5-18
Progress for WIPP infrastructure upgrade
2018-5-18
Perry scraps completion of US MOX facility
2018-5-18
Rosatom expands overseas links with new agreements
2018-5-18
NWMO broadens its international cooperation
2018-5-11
FirstEnergy responds to PJM grid reliability findings
2018-5-11
Nuclear for US grid resilience and climate
2018-5-10
Dome installed on Tianwan 6 containment building
2018-5-10
Other signatories express support for JCPOA
2018-5-10
TVA completes major flood protection
2018-5-8
Robots get smarter to help with decommissioning
2018-5-4
Fuel supply contracts signed for Swedish reactors
2018-5-4
New cracks delay restart of Hunterston B reactor
2018-5-4
Training milestones for new plant operators
2018-5-4
First Energy responds to PJM grid reliability findings
2018-5-4
NASA successfully tests Kilopower reactor
2018-4-27
Philippines to draw up nuclear energy policy
2018-4-27
IAEA reviews safety at South Ukraine unit 3
2018-4-27
Fuel loading under way at Chinese AP1000
2018-4-27
Macron: Europe must prioritise emission reductions
2018-4-27
Iran's Bushehr I changes to TVS-2M fuel
2018-4-20
6th Annual Nuclear Information Technology China Forum
2018-4-20
2nd Nuclear Power Maintenance Tool Seminar
2014-9-19
The Preparation Meeting of the First International Nuclear Plant Operation and Maintenance Conference 2014 Successfully held in Shanghai.
2014-9-19
NNBCS2014 Concluded a Great Success on August 27-29 in Shanghai!
2014-7-21
China's Xi hails 'new horizons' in ties with Argentina
2014-7-21
China nuclear contractor seeks merger with CPIC
2014-7-11
Investment program for Slovenian repository
2014-7-11
Supercomputer team wins award for core work
2014-6-17
Chinese Premier expected to sign UK nuclear deal
2014-6-17
Changjiang 2 vessel put in place
2014-6-13
Fourth Yangjiang unit gets its dome
2014-6-13
Sogin, CGN cooperate on waste management
2014-6-13
China produces first AP1000 vessel
2014-6-12
The 6th Annual Nuclear New Build China Summit
2014-6-6
Fuel loading at Fuqing 1
2014-6-6
China schedules new nuclear power reactors
2014-6-6
Fukushima ice wall under construction
2014-6-3
China Association of Plant Engineering Consultants
2014-5-27
China, Iran agree to push bilateral cooperation to new stage
2014-5-12
Mining operations begin at Husab
2014-5-9
Yangjiang 2 approaches start up
2014-5-8
Ningde 2 in commercial operation
2014-5-4
MBIR reactor supplier selected
2014-4-28
Political discord places Lungmen on hold
2014-4-28
Landmarks for Chinese reactors
2014-4-22
The 6th Annual Nuclear New Build China Summit 2014 will start up on August 27th in Shanghai, China!
2014-4-22
NITF2014 Concluded a Great Success on April 10-11 in Shanghai!
2014-4-22
Accelerating the Progress of Nuclear Power Informatization, building a safe and high-efficiency operation environment! —NITF 2014 will Start up on April 10-11, 2014 in Shanghai, China!
2014-4-22
Expanding Your Company’s Value in Nuclear IT Industry——The 2nd Annual Nuclear Information Technology China Forum 2014 is Coming Back!
About Us
Who We Are
Our Culture
Nuclear Summit
Event Center
Professional Service
Industry Information
Project Consulting
Training Course
Event Outsourcing
Join Us
Job Opportunities
Career Development
Contact Us
Tel: (+86-21) 6073 7200
Fax: (+86-21) 6176 8133
Email: info@innchinc.com
 
© 2018 INNCH INTERNATIONAL CO.,LTD. All Rights Reserved 技术支持:上海网站建设