News
 Industry News  
 Company News  
 
Home > News > Industry News
Kansai details upgrade work at oldest Takahama units
2016-9-12

Kansai Electric Power Company has released a plan of safety improvement works it will carry out to extend the operating periods of units 1 and 2 of its Takahama nuclear power plant in Japan's Fukui prefecture beyond 40 years. Regulatory approval for operating the units for up to 60 years has already been granted.

Under revised regulations which came into force in July 2013, Japanese reactors have a nominal operating period of 40 years. Extensions can be granted once only and are limited to a maximum of 20 years, contingent on exacting safety requirements.

In June this year, the Nuclear Regulation Authority (NRA) approved a 20-year operating extension for Takahama units 1 and 2 - both 780 MWe (net) pressurized water reactors which began operating in 1974 and 1975, respectively. They become the first Japanese units to be granted a licence extension beyond 40 years under the revised regulations.

Plant owner Kansai yesterday presented a schedule for the safety improvement works that will enable the two units to continue operating beyond 40 years.

The utility said work to improve fire protection at the two units would begin this month and will be completed by August 2019. The work will involve the replacement of fire-resistant cabling and the installation of fire protection sheeting, as well as the installation of additional fire detectors and fire extinguishing facilities.

Work to replace the refueling water tank is also set to begin this month, with installation of the new tank and construction of a protective wall around the tank due to be completed by August 2019.

Kansai will also reinforce the existing concrete wall surrounding the containment vessel of each unit and will also install a secondary dome on their containment buildings. This work will begin in February 2017, with completion scheduled for August 2019 at unit 1 and November 2019 at unit 2.

The seawater intake facility of unit 2 is also to be relocated. Excavation of a new tunnel into the bedrock will begin in May 2017, following by the installation of piping. A protective wall will also be built around the new seawater intake facility, with work due to be completed in March 2020.

The existing central control panels of both units will also be replaced between April 2018 and August 2019.

Kansai said it will "proceed with implementation of the work plan - which was made up today place the top priority on safety - to allow for operation for 60 years."

Takahama 1 and 2 have been offline for periodic inspections since January 2011 and November 2011, respectively, and are progressing through the restart process. In April, the NRA confirmed the units meet new safety regulations. The units are the oldest of the seven reactors so far deemed to conform to the new safety standards.

Unit 3 of the Takahama plant resumed operation on 29 January. Takahama 4 was restarted on 26 February, but was taken offline again three days later following an automatic shutdown due to a "main transformer/generator internal failure". An injunction imposed by a district court on 9 March has kept both units idle.

Researched and written
by World Nuclear News

  
 
2018-7-12
Bruce Power, Rolls-Royce deepen digital collaboration
2018-7-12
First partner announced for New Brunswick SMR project
2018-7-11
China’s Sanmen 2 cleared for fuel loading
2018-7-11
Plasma plant starts operations in Bulgaria
2018-7-11
Bangladesh issues construction licence for Rooppur unit 2
2018-7-6
Daher to apply for NRC transport package certification
2018-7-6
Urenco to enrich reprocessed uranium
2018-7-6
ATS to provide automated solutions for Bruce detube
2018-7-6
Turboatom and Toshiba team up for turbine upgrades
2018-7-6
Tokai 2 passes safety screening
2018-6-29
EDF and Veolia partner on robotics and vitrification
2018-6-29
Halden Reactor to be decommissioned
2018-6-29
Rolls-Royce and CTEC to integrate I&C expertise
2018-6-26
Approval for decommissioning of Swiss reactor
2018-6-26
Chinese AP1000s pass commissioning milestones
2018-6-22
Darlington to supply molybdenum-99
2018-6-22
Regulator details Taishan 1 commissioning schedule
2018-6-22
Genkai unit 4 supplying power again
2018-6-22
Full-scale tests to start soon at Finnish repository
2018-6-22
GE Power starts Arabelle production for Hinkley Point C
2018-6-14
Decommissioning plan for Tokai approved
2018-6-14
Cooperation strengthens mining radiation protection
2018-6-14
Ontario Power Generation starts rebuilding Darlington 2
2018-6-14
Steam generators in place at Hongyanhe 5
2018-6-14
USA launches Summit supercomputer
2018-6-8
First criticality achieved at Chinese EPR
2018-6-8
SNC-Lavalin signs agreement on Bellefonte completion
2018-6-8
WIPP returns to routine operations
2018-6-8
ERA publishes closure plan for Ranger
2018-6-8
EDF agrees to nuclear energy cooperation with Brazil
2018-6-1
US energy regulators back Illinois legislation
2018-6-1
Toshiba scraps project to build ABWRs in Texas
2018-6-1
Kansai cuts power rates as reactors restart
2018-6-1
Olkiluoto EPR prepares for fuel loading
2018-6-1
France, Russia extend nuclear power cooperation
2018-5-25
Alliance launched to highlight nuclear on world stage
2018-5-25
New Jersey clean energy laws signed
2018-5-25
Belarus, Kazakhstan to cooperate in nuclear power
2018-5-25
Dome installed at first Fangchenggang Hualong One
2018-5-25
GNF to fuel Entergy BWRs with advanced fuel
2018-5-18
Belgium and China award simulator contracts
2018-5-18
Progress for WIPP infrastructure upgrade
2018-5-18
Perry scraps completion of US MOX facility
2018-5-18
Rosatom expands overseas links with new agreements
2018-5-18
NWMO broadens its international cooperation
2018-5-11
FirstEnergy responds to PJM grid reliability findings
2018-5-11
Nuclear for US grid resilience and climate
2018-5-10
Dome installed on Tianwan 6 containment building
2018-5-10
Other signatories express support for JCPOA
2018-5-10
TVA completes major flood protection
2018-5-8
Robots get smarter to help with decommissioning
2018-5-4
Fuel supply contracts signed for Swedish reactors
2018-5-4
New cracks delay restart of Hunterston B reactor
2018-5-4
Training milestones for new plant operators
2018-5-4
First Energy responds to PJM grid reliability findings
2018-5-4
NASA successfully tests Kilopower reactor
2018-4-27
Philippines to draw up nuclear energy policy
2018-4-27
IAEA reviews safety at South Ukraine unit 3
2018-4-27
Fuel loading under way at Chinese AP1000
2018-4-27
Macron: Europe must prioritise emission reductions
2018-4-27
Iran's Bushehr I changes to TVS-2M fuel
2018-4-20
6th Annual Nuclear Information Technology China Forum
2018-4-20
2nd Nuclear Power Maintenance Tool Seminar
2014-9-19
The Preparation Meeting of the First International Nuclear Plant Operation and Maintenance Conference 2014 Successfully held in Shanghai.
2014-9-19
NNBCS2014 Concluded a Great Success on August 27-29 in Shanghai!
2014-7-21
China's Xi hails 'new horizons' in ties with Argentina
2014-7-21
China nuclear contractor seeks merger with CPIC
2014-7-11
Investment program for Slovenian repository
2014-7-11
Supercomputer team wins award for core work
2014-6-17
Chinese Premier expected to sign UK nuclear deal
2014-6-17
Changjiang 2 vessel put in place
2014-6-13
Fourth Yangjiang unit gets its dome
2014-6-13
Sogin, CGN cooperate on waste management
2014-6-13
China produces first AP1000 vessel
2014-6-12
The 6th Annual Nuclear New Build China Summit
2014-6-6
Fuel loading at Fuqing 1
2014-6-6
China schedules new nuclear power reactors
2014-6-6
Fukushima ice wall under construction
2014-6-3
China Association of Plant Engineering Consultants
2014-5-27
China, Iran agree to push bilateral cooperation to new stage
2014-5-12
Mining operations begin at Husab
2014-5-9
Yangjiang 2 approaches start up
2014-5-8
Ningde 2 in commercial operation
2014-5-4
MBIR reactor supplier selected
2014-4-28
Political discord places Lungmen on hold
2014-4-28
Landmarks for Chinese reactors
2014-4-22
The 6th Annual Nuclear New Build China Summit 2014 will start up on August 27th in Shanghai, China!
2014-4-22
NITF2014 Concluded a Great Success on April 10-11 in Shanghai!
2014-4-22
Accelerating the Progress of Nuclear Power Informatization, building a safe and high-efficiency operation environment! —NITF 2014 will Start up on April 10-11, 2014 in Shanghai, China!
2014-4-22
Expanding Your Company’s Value in Nuclear IT Industry——The 2nd Annual Nuclear Information Technology China Forum 2014 is Coming Back!
About Us
Who We Are
Our Culture
Nuclear Summit
Event Center
Professional Service
Industry Information
Project Consulting
Training Course
Event Outsourcing
Join Us
Job Opportunities
Career Development
Contact Us
Tel: (+86-21) 6073 7200
Fax: (+86-21) 6176 8133
Email: info@innchinc.com
 
© 2018 INNCH INTERNATIONAL CO.,LTD. All Rights Reserved 技术支持:上海网站建设