OPG ready to go with Darlington refurbishment
2016-9-5

After six years of planning and preparations Ontario Power Generation (OPG) says it is "ready to execute" refurbishment of the Darlington nuclear power plant and remains within the CAD 12.8 billion ($9 billion) estimate for the project, which is to start next month.

The company's latest semi-annual performance report has just been published, outlining progress made through six years of detailed planning and preparations leading up to the official start of work. This will be marked by a milestone referred to as 'Breaker-Open': the official disconnection from Ontario's power grid ready to start work. The 40-month project to refurbish unit 2 will be the first of four such outages as all four of the plant's Candu units are refurbished over the next ten years.

The refurbishment comprises over 500 projects which OPG has subdivided into five work bundles: retube and feeder replacement, which involves removing and replacing the fuel channels, calandria tubes and feeders inside each reactor; turbine generators, consisting of inspections and repairs on the four turbine generator sets and replacement of analogue control systems with new digital control systems; steam generators, which includes mechanical cleaning, water lancing, inspection and maintenance work; and balance of plant, covering smaller projects to replace or repair components on both the nuclear and non-nuclear side, such as heavy water and cooling systems, electrical systems, piping and valve work.

All the necessary materials have been delivered to the site, training of workers has begun and a detailed execution plan has been drawn up ready for work to start on unit 2 in October. Preparations have included using a mock-up reactor, first to test tools and procedures and then to train staff.

"I'm pleased to report it's all systems go for Canada's largest clean energy project," OPG's senior vice president for nuclear projects Dietmar Reiner said yesterday. He said the refurbishment project will generate CAD14.9 billion in economic benefit for the province, and once complete will enable the plant to continue operating for a further 30 years.

The 3512 MWe plant supplies about 20% of Ontario's electricity and, to ensure a reliable supply of low-carbon power during the refurbishment program, OPG will seek regulatory approval to continue operating the Pickering nuclear power plant until 2024.

Researched and written
by World Nuclear News

  
 
2018-6-14
Decommissioning plan for Tokai approved
2018-6-14
Cooperation strengthens mining radiation protection
2018-6-14
Ontario Power Generation starts rebuilding Darlington 2
2018-6-14
Steam generators in place at Hongyanhe 5
2018-6-14
USA launches Summit supercomputer
2018-6-8
First criticality achieved at Chinese EPR
2018-6-8
SNC-Lavalin signs agreement on Bellefonte completion
2018-6-8
WIPP returns to routine operations
2018-6-8
ERA publishes closure plan for Ranger
2018-6-8
EDF agrees to nuclear energy cooperation with Brazil
2018-6-1
US energy regulators back Illinois legislation
2018-6-1
Toshiba scraps project to build ABWRs in Texas
2018-6-1
Kansai cuts power rates as reactors restart
2018-6-1
Olkiluoto EPR prepares for fuel loading
2018-6-1
France, Russia extend nuclear power cooperation
2018-5-25
Alliance launched to highlight nuclear on world stage
2018-5-25
New Jersey clean energy laws signed
2018-5-25
Belarus, Kazakhstan to cooperate in nuclear power
2018-5-25
Dome installed at first Fangchenggang Hualong One
2018-5-25
GNF to fuel Entergy BWRs with advanced fuel
2018-5-18
Belgium and China award simulator contracts
2018-5-18
Progress for WIPP infrastructure upgrade
2018-5-18
Perry scraps completion of US MOX facility
2018-5-18
Rosatom expands overseas links with new agreements
2018-5-18
NWMO broadens its international cooperation
2018-5-11
FirstEnergy responds to PJM grid reliability findings
2018-5-11
Nuclear for US grid resilience and climate
2018-5-10
Dome installed on Tianwan 6 containment building
2018-5-10
Other signatories express support for JCPOA
2018-5-10
TVA completes major flood protection
2018-5-8
Robots get smarter to help with decommissioning
2018-5-4
Fuel supply contracts signed for Swedish reactors
2018-5-4
New cracks delay restart of Hunterston B reactor
2018-5-4
Training milestones for new plant operators
2018-5-4
First Energy responds to PJM grid reliability findings
2018-5-4
NASA successfully tests Kilopower reactor
2018-4-27
Philippines to draw up nuclear energy policy
2018-4-27
IAEA reviews safety at South Ukraine unit 3
2018-4-27
Fuel loading under way at Chinese AP1000
2018-4-27
Macron: Europe must prioritise emission reductions
2018-4-27
Iran's Bushehr I changes to TVS-2M fuel
2018-4-20
6th Annual Nuclear Information Technology China Forum
2018-4-20
2nd Nuclear Power Maintenance Tool Seminar
2014-9-19
The Preparation Meeting of the First International Nuclear Plant Operation and Maintenance Conference 2014 Successfully held in Shanghai.
2014-9-19
NNBCS2014 Concluded a Great Success on August 27-29 in Shanghai!
2014-7-21
China's Xi hails 'new horizons' in ties with Argentina
2014-7-21
China nuclear contractor seeks merger with CPIC
2014-7-11
Investment program for Slovenian repository
2014-7-11
Supercomputer team wins award for core work
2014-6-17
Chinese Premier expected to sign UK nuclear deal
2014-6-17
Changjiang 2 vessel put in place
2014-6-13
Fourth Yangjiang unit gets its dome
2014-6-13
Sogin, CGN cooperate on waste management
2014-6-13
China produces first AP1000 vessel
2014-6-12
The 6th Annual Nuclear New Build China Summit
2014-6-6
Fuel loading at Fuqing 1
2014-6-6
China schedules new nuclear power reactors
2014-6-6
Fukushima ice wall under construction
2014-6-3
China Association of Plant Engineering Consultants
2014-5-27
China, Iran agree to push bilateral cooperation to new stage
2014-5-12
Mining operations begin at Husab
2014-5-9
Yangjiang 2 approaches start up
2014-5-8
Ningde 2 in commercial operation
2014-5-4
MBIR reactor supplier selected
2014-4-28
Political discord places Lungmen on hold
2014-4-28
Landmarks for Chinese reactors
2014-4-22
The 6th Annual Nuclear New Build China Summit 2014 will start up on August 27th in Shanghai, China!
2014-4-22
NITF2014 Concluded a Great Success on April 10-11 in Shanghai!
2014-4-22
Accelerating the Progress of Nuclear Power Informatization, building a safe and high-efficiency operation environment! —NITF 2014 will Start up on April 10-11, 2014 in Shanghai, China!
2014-4-22
Expanding Your Company’s Value in Nuclear IT Industry——The 2nd Annual Nuclear Information Technology China Forum 2014 is Coming Back!
About Us
Who We Are
Our Culture
Nuclear Summit
Event Center
Professional Service
Industry Information
Project Consulting
Training Course
Event Outsourcing
Join Us
Job Opportunities
Career Development
Contact Us
Tel: (+86-21) 6073 7200
Fax: (+86-21) 6176 8133
Email: info@innchinc.com
 
© 2018 INNCH INTERNATIONAL CO.,LTD. All Rights Reserved 技术支持:上海网站建设